Working Days
The finish date of each task is calculated using its start date and its working duration. The check boxes in the Working Days group of the Gantt Chart form, can be used to define which working days are taken into account when the finish date of a task is calculated.
Shading
The Shading check boxes are used to define which days are shaded (greyed out) in the background of the Gantt Chart. You may need to zoom-in on the chart to be able to see the shading.