Break

On the Scheduling | View tab, in the Interactive Dependencies group: Select an option from the Break menu to remove tasks from the dependency chain based on their position relative to the currently selected task(s).

The Vizex Link Dependencies layer will be updated accordingly. On the title bar of the application window, you can click Undo to undo the last action.

Selected

Delete all links in the dependency chains between the selected tasks.

Note: This will break dependencies between the selected tasks, while dependencies between tasks that are selected and tasks that are not will remain.

Previous

Remove the immediate predecessor links of the selected task(s).

All Before

Remove all predecessor links of the selected task(s).

Next

Remove the immediate successor links of the selected task(s).

All After

Remove all successor links of the selected task(s).

Previous and Next

Remove the immediate predecessor link and the immediate successor link of the selected task(s).

All Before and After

Remove all predecessor and successor links in the dependency chain.

Bypass Task

Remove the selected tasks from the dependency chain

All Shown

Remove all shown tasks (based on the active filter).

All

Remove all dependencies of all types.