Interactive Dependencies
When tasks are added to the schedule, they are automatically linked. To modify the dependencies between tasks, use the tools provided on the Scheduling | View tab, in the Interactive Dependencies group:
-
Click Link Adjacent to build horizontal dependencies by linking adjacent tasks, commencing from the selected starting task.
-
Click Link to create a chain of dependencies between selected tasks, based on the order of selection.
-
Click Assign New Sequence to resequence tasks in the order in which their wireframes are selected in Vizex.
-
Click Resequence Selected Tasks by String to resequence the cached layer using a string which passes through the mining blocks.
-
Click Horizontal by Index to build horizontal dependencies by using the block index attribute to gain awareness of the relationships between tasks.
-
Select Vertical | By Index to build vertical dependencies between selected tasks (mining blocks) using an index attribute.
-
Select Vertical | By Index using Slope Angle to build vertical dependencies between selected tasks (mining blocks) using an index attribute and a specified slope angle.
-
Select Vertical | For Bench Solids to build vertical dependencies between bench solids for one or more pits using extraction number, bench Z and optional pit identifier.
-
Select Vertical | For Analysis Case to build vertical dependencies between bench solids for a simple analysis case using the Pit Shell Number, Bench Z and an optional Pit Identifier as inputs.
-
Use the options on the Show menu to toggle the display of dependencies in the Gantt Chart on and off, based on type.
-
Select an option from the Break menu to remove tasks from the dependency chain based on their position relative to the currently selected task(s).