Linked Tasks
-
When one or more tasks are selected, select an option from the Tasks Before menu to:
-
select the previous task
-
select all tasks before the selected tasks
-
When one or more tasks are selected, select an option from the Tasks After menu to:
-
select the next task
-
select all tasks after the selected tasks
-
Select All Before and After to select all tasks that are linked to the currently selected tasks.
-
When tasks are selected, select Unlinked Tasks to reduce the selection to include only those tasks that are not linked to any other tasks in the schedule.
-
Select All Unlinked Tasks to select all of the tasks that are not connected to any other tasks in the schedule.