Select
-
When one or more tasks are selected, select Tasks in Same Group to select all shown tasks in the group to which the selected tasks are assigned, or in the selected task groups.
-
When one or more tasks are selected, select Tasks of Same Type to select all shown tasks that have the same type as the selected tasks.
-
Select All Tasks to clear the current selection and selects all linked tasks that are currently shown (as determined by the active filter).
-
Select Scheduled Start Task to select the scheduled start task.
-
Select Go to Today to show today in the bar chart view of the Gantt Chart.
-
Select Scheduled End Task to select the scheduled end task.
-
Select Critical Path to select all of the tasks on the critical path of a group of linked tasks.
This option requires the selection of one or more tasks (or right-click on a task and select the Critical Path option).