Dump Sequences
Overview
The Dump Sequences step is a prioritised list of dumps for the schedule to follow. Dump sequence entries can later be referenced in the Destination Rules step.
Note: You can setup destinations using individual dumps and/or dump sequences, however you will need at least one dump sequence to progress to the next step.
Dump Sequences step overview
Adding Dump Sequence
-
Click the blue plus icon located in the toolbar.
-
Rename the sequence to the desired name.
-
Place entry into the relevant folder (optional).
Avoid using commas in the Dump Sequence name, because when exporting future reports to CSV, the commas result in misalignment of the columns.
Configuring Dump Sequence
-
Click inside the Sequence panel. The Configure dialog will appear.
-
Click theblue add button.
-
Click inside the blank panel of the new entry.
-
Select dump records.
-
Repeat steps 2-4 to add more dumps to the sequence.
Dumps sequence configuration
Multiple dumps can be selected for each priority. Which dump is chosen will depend on which are available and then haulage distance or cycle time.
-
Use the Eraser tool to clear all flags of selected dumps and lifts.
-
Press View Database button to open project records preview window.
Choose Records preview window