Crushers
Every project must have at least one crusher, which represents a transformation of an input material (such as mined tonnes) into an output material (such as product tonnes).
List of crushers used in a project is given in the Crushers step.
Crushers step overview
|
Column |
Usage |
Notes |
|---|---|---|
|
Crusher Name |
Name of Crusher. |
Automatically added from Site Lists. |
|
Capacity Field |
Field used in calendar when setting crusher rate per hour. |
|
|
Report Feedable Stocks |
Used to select if crusher will be used to report feedable stock. |
If one crusher is predecessor to another, then feedable stocks will report tonnes that are before the first crusher at both crushers. Example: Blasted blocks in the pit will be reported as feedable for a primary crusher as well as the main plant. This is because the tonnes must go through the primary to get through to the main plant. |
To add crushers:
-
Go to Haul Infinity > Network tab:
-
Select a node, right-click and promote to Crusher.
-
-
Go to back to APS > Setup tab > Site Lists step > Crushers field:
-
press the blue plus icon to add a crusher.
-
-
Go to the Setup tab > Crushers step:
-
select a capacity field from the drop-down.
-
Crushers must be represented by a node in Haul Infinity. The node name must follow the convention “Crushers/myCrusherName”.