Work Schedules
The Work Schedule step represents a collection of recurring operational delays. Work schedules can be created for various mining operational groups, such as Production and Development, to capture distinctive delay schedules.
Work Schedule step overview
The <Full Time> work schedule is a default schedule and can’t be edited.
To add a Work Schedule:
-
Click theblue plus icon.
-
Select the a field from the Name column and rename it, i.e. “Mining”.
To add Delays into the Work Schedule:
-
Select the applicable Work Schedule.
-
Click theblue plus icon.
-
Choose a delay from the Type drop-down list.
-
Configure the delay in the Configuration drop-down window.
Delays Configuration in the Configure dialog:
|
Section |
Description |
|---|---|
|
Recurring Delay |
Untick if the delay is a singular occurrence |
|
Time of Day |
Set the start time of the delay as well as the duration
|
|
Recurrence Setup |
Daily - specify the recurrence at a daily granularity.
Weekly - specify the recurrence at a Weekly granularity.
Monthly - specify the recurrence at a Monthly granularity.
Yearly - specify the recurrence at a Yearly granularity.
|
|
Recurrence Range |
The overarching duration in which the delay will be applied. Start date - specify the start date from which the delay will take effect. End Date:
|