Bridge Rehandle Example

Demonstration model available at the top of this guide.

Video demonstration can be found here: https://www.youtube.com/watch?v=Lu0DALjYaAI

Thus far this guide has focused on coal stockpiling. This next example demonstrates how to set up waste rehandle as a stockpile process to create inpit bridges.

The steps for setting up a waste rehandle process as a stockpile are the same as those explained above. You will need to:

  1. Create records on your Source and Destination table with the same volume

  2. Set up a stockpile in the Scenario > Settings > Stockpile that creates a link between your Source and Destination records

  3. Create a Process for the stockpile and assign it a Source Quantity, Destination Quantity, Initial Percentage Completed and Solid

  4. Preschedule your Source Table stockpile records (for applicable records)

  5. Ensure that at least one piece of equipment has the newly created stockpile Process ticked On

  6. Add the Destination Table stockpile records to a Destination Path

The above steps are the bare basics of setting up a rehandle stockpile. The next stage is creating dependencies to incorporate the dump and dig elements of the stockpile into the overall schedule. See the video above and the demonstration model at the start of this guide for examples.