Bench Offsets
Bench Offsets may be used to force a delay and minimum or maximum vertical lag between phases.
Bench Offsets step overview
To add a Bench Offset:
-
Click theblue plus icon to add a new dependency set.
-
Rename the dependency set (i.e. mining rules, backfill rules, land-bridge rules).
-
Using the tree hierarchy on the right, select the successor record and double click on the predecessor.
-
Set the delay in hours.
-
Set vertical offset in the Vertical Offset column in metres:
-
negative to keep the successor elevated over the predecessor,
-
positive to keep the predecessor elevated over the successor.
-
Verify the dependencies in the Preview panel.
Every bench at elevation “E” in the Successor stage is made dependent on the bench at elevation “E+Offset” in the Predecessor stage. Offsets may be positive or negative.