Highlight Tasks in the Animation

  1. On the Home tab, in the Results group: Select Gantt Chart to open the Gantt Chart Window.

  2. Right click on the (Schedule) tab header and select Open New <Name> Window (where <Name> is the name of the active Case.

  3. On the Home tab, in the Results group: Select Animation to open the Animation Window.

  4. In the Animation window, right click on the (Animation) tab header and select New Vertical Tab Group.

  5. The Gantt Charts window and the Animation window are displayed side-by-side.

Highlight Selected Tasks

  1. On the Home tab, in the View group: Select Animation Options | Highlight Selected Steps.

    The tasks you select in the Gantt Chart are highlighted in the Animation Window: