Development Sequence Dependencies

Add

Development Sequence dependencies are generated from all internal dependencies in the Development Network Layer, based on their Cut, and are case-specific.

To view dependencies in the Animation Window, enable Annotate Dependencies and then select the Development Sequence Dependency from the Annotate Dependencies > Network Attach > right-click menu.

When you add or edit a Dependency of this type, you can set the following parameters (or accept the defaults where applicable):

Description

Optionally, enter a Description that can be used with the Name to further identify the Dependency. Detail useful for diagnosing issues with Dependencies should be added here.

Treat Predecessors as OR Group

Where multiple predecessor tasks have the same successor task and the OR check box is NOT enabled, the successor task will only be released after ALL of the predecessor tasks are completed.

Where multiple predecessor tasks have the same successor task and the OR check box is enabled, then the successor task will be released when ANY of the predecessor tasks are completed.

Priority

The Priority is a numerical method to classify your dependencies by importance. Ranges with Priority 1 will be resolved first, meaning if there are conflicting dependencies between two or more ranges, ranges with lower priority will become circular, rather than randomly resolving the conflict.

Act As Constraint

Normally a Dependency takes into consideration the relationship between Tasks regardless of the Equipment or Date involved. Selecting the Act As Constraint check box on your Range, Offset or Field Offset Dependency adds a significant amount of power such as Time conditionals (Start and End Date) as well as Equipment conditions.

For example, if the user ticks act as constraint in the dependency range, and excludes Jumbos, the Jumbos will not honour the dependency range.

Set the Source (Text Range or [Inline] *) Range that applies to the Tasks. See: Text Range and Inline Ranges.

Release Delay Expression

Once a Predecessor Range has been completed, the Release Delay controls how long until the Successor Range is considered "Released" and can be worked. Accept the default (None) or build a Release Delay Expression using the operators, constants and functions provided by the Expression Editor.

A common user case example is to use release delays between paste filling (for example, 21 days) and subsequent adjacent drilling or bogging activity.

See: Released vs Unreleased

Predecessor/Successor Range

By default, the predecessor and successor range for the Development Sequence dependency is set to everything ([Inline]*). This ensures that all the generated development solids from the Development Network Layer are connected based on their cut and direction.

In rare instances where the user might not want the internal connections to be done automatically, they can exclude the range for those solids.


Development Sequence Dependencies

Predecessor/Successor Processes

Allows you to control which Processes are used for the Dependency.

Reverse Direction

If the user wants to connect their internal dependencies in opposite directions to the Development Network Design, they can do so by ticking the Reverse Direction box.

Link between Development Network Design and Development Sequence Dependency

It is important to note that the mining direction in the Development Sequence Dependency is driven by the direction of the centrelines in the Development Network Design. Therefore, if the user changes the direction of a tunnel dependency that belongs to the Development Sequence, it will automatically change the direction of the centreline in the Development Network Design and vice versa: if the user changes the direction of a centreline, it will automatically revert the dependency direction associated with that centreline.

Use Node Sorting Sequence

Select this check box when path nodes have been ordered based on their positions and attributes as defined in an ordered list of Sorting Entries or Node Sorting Sequence. Node Sortings facilitate a degree of “auto-scheduling” by allowing tasks to be worked using an arbitrary ordering of nodes which might be intended, for example, to target the highest grade, or work in a structured order not specified by the level structure.

Node Sorting Sequence

Use the drop-down to select a Node Sorting Sequence. Alternatively, click on the ellipsis to edit or create Node Sortings.