Stope on Dev Rule
The Stope on dev Rule is determined by looking at the intersection between development and stopes. In the case of an intersection, a rule is created from stope to development to indicate that the stope will follow the completion of the development.
When the Stope on Dev Rule check box is selected in the Import Stopes dialog, any stopes that do not have development network intersections are added to an "UNSET" range.
Stope on Dev Dependencies are listed under Dependencies:
The Stope on Dev rule is only recommended for high level sequence assessments. For more established models, it is better to define Geometric or Offset dependency rules to connect development to stoping activities.