Equipment
The Equipment tab of the Snapshot Viewer will show you Source Paths and (when relevant) Destination Paths for each piece of Equipment in your Schedules for incomplete Tasks.
Remember that each Task can be right-clicked or double-clicked for more information. Destination Paths will appear in Bold if they are related to the Active Source Task for the Equipment.
Destination Paths that are not available to that Equipment will not appear at all.
Note: If a Task appears Available but is not Active, ensure that Allow Advance is being used (where relevant) and that the Task is not Constrained.
Related to Path Commands: When Allow Advance is turned On it allows the schedule to look further down the path to find Released Tasks (or until Allow Advance is set to Off). Allow Advance will only have an effect when there are Dependencies or Constraints set. The default is Off.
A Usages tab is available when you right-click on a task iand select Find Usages.