Equipment
Use the Equipment tab of the Gantt Settings window to control the colours of each piece of equipment shown on the chart.
Colours
Click on a Colour, Background Colour Header colour patch to choose from a palette of standard colours or add a custom colour. Colours may also be expressed as RGB values in the Bulk Editor (see below).
Note that the Header Text Colour and Appointment Border Colour columns will not appear if the Automatic Caption Colour and Automatic Job Border Colour options are selected on the Gantt Chart Settings tab.
Bulk Editor
Click the Bulk Editor button (on the far right of the page) to make bulk changes to the items on the page using the spreadsheet functions provided by the application.
For more information, see: Bulk Editor