On the Scheduling | View tab, in the Gantt Chart group: Click Columns to set the order and the visibility of the columns in the Gantt Chart.

To change the order of the columns, use the Up and Down arrows on the list toolbar.

To change the visibility of the columns, select and deselect the check boxes to toggle column visibility on and off. You can use the clear button on the list toolbar to turn the visibility of all columns off, before making you selections.

Template

The Template button is only available for Template Forms. Template Forms inherit saved or previously used values.

Click the Template button to select and open a saved form set template.

Load Template

Click the Load Template button to select and open a saved template to populate the fields of the form.

Save Template

Click the Save Template button to save the details of the current form as a template that can be loaded at a later time.

Manage

Click the Manage button to open the Template Forms manager which can be used to open, save, delete, import and export the template forms for your project.

Undo and Redo

Click Undo (CTRL + Z) to undo recent changes in the form. After an Undo, click Redo (CTRL + Y) to restore the last change that was undone.

Collapse

Collapse (roll-up) the form to preview a chart, or preview the results of an operation in Vizex, or obtain input values from Vizex, the Property Window, the File Editor, or the Plot Editor.