Import Development Network Data
A case that has the Data > Development Network option enabled as part of its Scenario Settings is able to support underground mine scheduling and reserving. Inputs to the process are Centreline strings which represent a Development Network and Solids which represent the stopes to be mined. From these, a set of scheduling solids are generated under a "Development Network Layers" node of the Design Data pane.
Attribute Fields mapped and synchronized with a Data Table and a Development Network Layer can be exported to a <Table_Name> Development Network Layers.xml file. This allows the same file to be imported to restore a snapshot of a development network associated with a case, or to share development network data across different cases.
To import network development layer data and (optional) attribute fields to a data table:
-
Right-click on the Table in the Project Explorer and select Import | Development Network Data:
You will be prompted to navigate to the folder location of a <Table_Name> Development Network Layers.xml file that was previously exported.
-
If Attribute Fieldswere exported that cannot be matched to existing fields, you will be prompted to either ignore or import and create those attributes (or Cancel):
If you choose to import and create missing or mismatched attributes, a summary of the attributes that were imported is shown.
Click Close to close the dialog.
Click Export to export the list of attributes to an xlsx file.