Add Subtask

A task may comprise one or more subtasks. To create a subtask:

  1. On the Navigation menu, click Tasks to open the Task Manager window.

  1. Select a task in the Gantt:

  1. Click the Add subtask button:

    You can also open the Task from the Gantt chart and use the menu to select Add Subtask.

Properties

Set the following properties of the sub task:

Create

Finally, click Create to create the subtask. The new subtask is added under its parent on the Gantt chart.