EH3: Equipment Hours by Period
EH3: Equipment Hours by Period
Description: |
---|
A summary of the time selected equipment spent in selected states for a defined period. |
Short-range planners can use this panel with short periods (e.g. each shift for a week) to compare each vehicle’s activities against their plans. |
Associated panels: | |
---|---|
EH1: Equipment Hours | A summary of the hours spent in each of the selected states by each of the selected pieces of equipment for the defined period. Run this report on a group of equipment (e.g. all bolters), to understand how their time is spent performing various tasks in the mine. |
EH3: Equipment Hours by Period | A summary of the time selected equipment spent in selected states for a defined period. |
EH5: Equipment Timeline | A comprehensive report on the date, start time and duration that selected equipment was in one of the selected states during the defined period. |
Terms used: | |
OID | One or all of the operating, idle and down states. |
Panel Definition: | |
A panel is defined by a set of report parameters and attributes which may vary from site to site: |
|
Parameter | Attributes |
Site | Select from the list of configured sites. |
Period | Year, Month, Day Shift, Macro. |
Equipment | The unit of equipment assigned as Secondary Unit. |
Crew | All Crew, Crew. |
Status | All States, Group, Type, Category, Detail. |
Summary levels: |
---|
The final report will include data at the Attribute level for the following Parameters: Period, Equipment and Status. |
Data capture method: | ||
---|---|---|
Paper log | Voice radio | Automated network |
Target audience: | ||||
---|---|---|---|---|
Management | Engineering | Geology | Survey | Maintenance |
Personnel | Control Room Operator | Contractors | Drilling | Production |