Establish Without Constraining

Establish Without Constraining allows the schedule to mine an initial quantity of material (equal to the Reentry Quantity) without applying grade limits.

What it does

  • Lets the tool “build inventory” first.

  • Enables blending where all available material initially falls outside the grade band.

    For Example, if target blend is 5–10% and you only have:

    • 2% stope

    • 12% stope

Without this option:

® Neither is allowed.

® Schedule stalls.

With this option:

® It mines some 2% and some 12%.

® Blends to fall within the band.

® Then constraints activate.

Downside

It can cause the final overall grade (period total) to fall outside min/max bounds.

Upside

The schedule completes instead of dry-cutting or stalling.