Establish Without Constraining
Establish Without Constraining allows the schedule to mine an initial quantity of material (equal to the Reentry Quantity) without applying grade limits.
What it does
-
Lets the tool “build inventory” first.
-
Enables blending where all available material initially falls outside the grade band.
For Example, if target blend is 5–10% and you only have:
-
2% stope
-
12% stope
-
Without this option:
® Neither is allowed.
® Schedule stalls.
With this option:
® It mines some 2% and some 12%.
® Blends to fall within the band.
® Then constraints activate.
Downside
It can cause the final overall grade (period total) to fall outside min/max bounds.
Upside
The schedule completes instead of dry-cutting or stalling.