Setup
This

Post Schedule Tasks
In the Scenario Settings window, on the Post Schedule Tasks tab, two new tasks can now be added:
-
Run Case As a post schedule task of the current case, run the schedule for another case.
-
Run Script Specify a script to run after the schedule has run.
Select the Lock Start Date check box to ensure that the case to be run as a post schedule task has the same start date as the parent case (to synchronise the two cases).

The Source Path syntax has been extended to allow a Start Date and an End Date to be set for a set of tasks. An End Date Behaviour flag can also be set which allows two states:
-
Ignore - the end date is only a suggestion
-
Constraint - the end date is respected in source step selection