Filters
On the Filters tab of the Gantt Settings window, you can now filter by a specified Start Time (defaults to Schedule Start) and End Time (defaults to Schedule End).
You can also filter by Source Range and Destination Range (each range defaults to an Inline “*” (all) range.
When the Output Schedule window is open, you can now select an Export Schedule to Project Spreadsheet Document option (from the Import/Export menu on the application window title bar) to generate a representation of the Output Schedule.
Filters applied to the schedule will also apply to the export.