MM3: Equipment Measures by Location

MM3: Equipment Measures by Location

Description:
For each piece of selected equipment the measure types associated with a source during the defined period is listed. The measure type and the source are selected. The total measures for each piece of equipment for the period are included.
Associated panels:
GC2: Daily Production The tonnage of material moved from a selected source to a selected destination during the defined period is reported. The defined grade types of the material are presented as grades and contained metal values. As there may be numerous grade types defined, each row may cover more than one page.
MM7: Equipment Measures by Period - Location For each piece of equipment at one of the selected locations the amount of selected material displayed. The equipment and the measure type are selected. The report can be presented for the year, month, day or shift of the defined period. Totals are presented for each equipment-location group, the overall total for each piece of equipment and the overall total for all the equipment.
MM13: Material Movements The amount of material moved from one of the selected sources to one of the selected destinations during the defined period. The total material moved during the period for each source-destination group and the overall total are included.
Terms used:
Bogger A term used to describe a loader, typically a loader operating in an underground environment.
Panel Definition:
A panel is defined by a set of report parameters and attributes which may vary from site to site:
Parameter Attributes
Site Select from the list of configured sites.
Period Year, Month, Day Shift, Macro.
Equipment The unit of equipment assigned as Secondary Unit.
Source All Material, MineArea, Minelevel, Loctype, Dev/Prod, Material Type, Capital/Operating, Flowtype, Panel, Location.
Measure Select from the list of available values.
Summary levels:
The final report will include data at the attribute level for the following parameters: Equipment and Status.
Data capture method:
Paper log Voice Automated
Target audience:
Management Engineering Geology Survey Maintenance
Personnel Control Room Operator Contractors Drilling Production