Configure a task template
Task Templates are created for a set of operations. They should be set up in the same order that the operations are performed, for example, Drilling, Charging, Firing, etc.
Task Templates are configured in Reference Data > Configuration Items > Miscellaneous. There are two tables that can be deployed which correspond to Equipment and Location tasks:
ShiftPlanEquipmentTaskTemplate:
ShiftPlanLocationTaskTemplate:
Equipment
An example of an equipment task template definition is shown below:

TemplateGroup
The group that the task belongs to.
Equipment
A specific piece of equipment can be assigned to perform the task.
Primary Status
The status of the equipment from the Status group in Reference Data.
Location
The location where the task will be performed.
Measure
The measure to be applied to the task.
MeasureValue
The value of the measure.
Destination
If applicable, the destination the equipment is assigned to.
Material
If applicable, the material associated with the equipment and its destination.
StartupDelayHours
The time between the previous task and the next. This only applies when you create tasks by dragging and dropping the entire template group. It does not apply when drag and dropping individual tasks.
DurationHours
The time that the task will take to complete.
Display Colour
The colour used to display the task in the shift planner.
Order
The order of the task in the sequence of tasks. Tasks should be set up in the same order that the operations are performed. i.e. Drilling, Charging, Firing, etc.
Location
An example of a location task template definition is shown below:

TaskTemplateGroup
The group that the task belongs to.
LocationStatusClassification
The status classification that the location belongs to.
LocationStatus
The initial status of the location.
TaskType
Task type as ‘location’.
Location
The location where the task will be performed.
Measure
The measure to be applied to the task.
MeasureValue
The value of the measure.
StartupDelayHours
The time between the previous task and the next.
DurationHours
The time that the task will take to complete. It does not apply when drag and dropping individual tasks.
Display Colour
The colour used to display the task in the shift planner.
Order
The order of the task in the sequence of tasks. Tasks should be set up in the same order that the operations are performed. i.e. Drilling, Charging, Firing, etc.