Create Subtask
A task may comprise one or more subtasks. To create a subtask:
-
On the Navigation menu, click Tasks to open the Task Manager window.
-
Select a task in the Gantt:
-
Click the Add subtask button:
You can also open the Task from the Gantt chart and use the menu to select Add Subtask.
Properties
Set the following properties of the sub task:
Create
Finally, click Create to create the subtask. The new subtask is added under its parent on the Gantt chart.